Waste-to-Energy Plant Stapelfeld

Together with the construction company Matthäi, the construction of the component including TGA (lot 1) for the construction of a new waste heat power plant for thermal waste recycling for untreated and processed commercial and household waste as well as a mono-sewage sludge incineration plant (KVA) at the Stapelfeld site will take place.

Slip form: approx. 44,000 m²
Concrete: approx. 29,000 m³
Rebar: approx. 4,000 t